Survey time!
How would you spread the labour effort across a typical, generic, vanilla-flavoured Networks project?
Now I know I know... no two networks projects are the same and there is a big difference between installing one firewall and deploying a whole global MPLS network. But I want people to generalise here and spread 100% of effort across the following project headings:
[Assume what you need to for the project headings]
1) Initiation
2) Discovery
3) Design
4) Development
5) Deployment
6) Handover to Ops
7) Closedown
8) Project Management [separate out the PM time here]
=100%
I plan to collate and let people know the results, so please have a go by leaving your estimate in the comments below.
Cheers
Rob
Thursday, 16 August 2007
Estimating the proportions of a networks project - have a go!
Posted by Rob at 23:39
Labels: Estimating, Network, Project Management
Subscribe to:
Post Comments (Atom)


1 Comment:
1) Initiation 5%
2) Discovery 10%
3) Design 20%
4) Dev 5%
5) Deployment 40%
6) Handover 5%
7) Closedown 1%
8) PM 14%
=100
Post a Comment